gold processing plant , Seligdar | 25 March 2025 г. | 12:01

Seligdar completed over 60% of total amount of work at gold plant of Khvoyny project

Seligdar completed over 60% of total amount of work at gold plant of Khvoyny project

Polymetallic Holding Group Seligdar (hereinafter referred to as the Holding Group, Seligdar; MOEX: SELG) is on track with the works on construction of the gold processing plant within the Khvoyny project.

Currently, more than 85% of metal structures, 76% of sandwich panels and 60% of roofing structures have been installed, and 98% of the foundations for all future production facilities have been completed. The overall readiness of the facility reached 60%.

Earlier, with coming of the cold weather, the builders closed the thermal circuits with heat supply on the main building and the filtration building, where currently technological equipment, technological pipelines, cable-carrying systems and interior spaces are being assembled.

Mill equipment, storage equipment (leaching agitator tanks, etc.) is being installed in the sorption, desorption, and reagent preparation units and oil stations are being connected.

Installation of floors and technological walls is coming to an end in the filtration building, and the installation of conveyors has begun. Bunkers and plate feeders have been installed at the ore preparation and acceptance site, and work is underway to install conveyor and crushing equipment.

Earlier, at the end of 2024, permission was received to commission a 110/6 kV power substation, and work on the installation of a diesel power substation is nearly completed.

The commissioning of the gold processing plant is scheduled for 2025, and full ramp-up is scheduled for 2026. The design capacity of the factory is 3 million tonnes of ore and 2.5 tonnes of gold per year.

Source: Seligdar